Dutton Park Rail Station Brisbane
LOCATION:
Brisbane, QLD
CASA ROLE:
Sub-Contractor
CLIENT:
Queensland Rail
CONTRACT VALUE:
$3,600,000
COMPLETION DATE:
May 2024
KEY SKILLS:
PROJECT SCOPE: Dutton Park Rail Station Brisbane
CASA were engaged to supply and install new platform structures as part of the Dutton Park Rail Station relocation. Structures included a 50-metre cranked footbridge, bridge support column, canopies and stair towers.
The footbridge required off-site preassembly of the structure and partial fitout to reduce the disruption to local roads and rail services.
Dutton Park Rail Station key points:
- Works completed in suburban Brisbane
- Works fabricated to MRTS78 specifications
- Installation occurred during the weekend closure of rail and local roads
- The footbridge was made up of three sections which were fitted out before lifting into position
- The footbridge was installed without the need for temporary works, thereby reducing the rail closure time