Dutton Park Rail Station Brisbane

LOCATION:
Brisbane, QLD
CASA ROLE:
Sub-Contractor
CLIENT:
Queensland Rail
CONTRACT VALUE:
$3,600,000
COMPLETION DATE:
May 2024
KEY SKILLS:

PROJECT SCOPE: Dutton Park Rail Station Brisbane

CASA were engaged to supply and install new platform structures as part of the Dutton Park Rail Station relocation.  Structures included a 50-metre cranked footbridge, bridge support column, canopies and stair towers.

The footbridge required off-site preassembly of the structure and partial fitout to reduce the disruption to local roads and rail services.

Dutton Park Rail Station key points:

  • Works completed in suburban Brisbane
  • Works fabricated to MRTS78 specifications
  • Installation occurred during the weekend closure of rail and local roads
  • The footbridge was made up of three sections which were fitted out before lifting into position
  • The footbridge was installed without the need for temporary works, thereby reducing the rail closure time